Enhancing Classroom Lighting with Ovia Inceptor A-LITE LED Battens
A primary school required a complete lighting upgrade to replace outdated fluorescent fittings that were inefficient and no longer fit for purpose. The aim was to improve energy efficiency, enhance the learning environment, and meet current safety compliance standards—all within a tight 2-day installation window during half-term.
Prowired Electrical partnered with Ovia to supply and install high-performance Inceptor A-LITE LED battens and emergency lighting across the school, delivering brighter, safer, and more sustainable classroom lighting.
Delivering a Safe and Efficient LED Upgrade
Our team approached the project with a clear plan to minimise disruption and maximise impact. The works were carried out entirely over a weekend and school break, ensuring no interruption to teaching. Legacy wiring issues and outdated ceiling mountings were swiftly addressed, resulting in a neat, consistent, and high-performing installation throughout the premises.
Key Services Delivered:
- Installation of Ovia Inceptor A-LITE LED battens across classrooms and corridors
- Emergency lighting installation to meet compliance standards
- Adaptive mounting solutions for legacy fixture compatibility
- Completion of works within a restricted access schedule during school holidays
- Post-installation testing and verification for safety and efficiency
Contact Prowired Today!
Project Outcome
The project was completed on time and within scope, transforming the school’s lighting while delivering long-term cost and energy benefits.
Key Benefits Delivered:
- Energy Efficiency – High-efficiency LEDs (up to 120 lm/W) drastically reduce power consumption
- Enhanced Learning Environment – Uniform, flicker-free lighting improves student visibility and focus
- Long-Term Value – 50,000-hour lifespan and 5-year warranty reduce future maintenance and costs
- Safety & Compliance – Emergency lighting meets current regulations, and all fittings installed to IP20 and IK06 standards
- Disruption-Free Execution – Work completed entirely during the half-term break to avoid interference with school activities